| Unit | Capacity Reduction (MW) | Cause | Start Date | Start Time | Expected Return to Service From | Expected Return to Service To | Date Notified |
|---|---|---|---|---|---|---|---|
| T-MRWD-1 | 450 | Boiler | 27/10/2021 | 04:45 | 27/10/2021 | 27/10/2021 | 27/10/2021 03:51:07 |
| T-MRWD-1 | 475 | Planned Outage | 06/04/2023 | 14:00 | 06/04/2023 | 06/04/2023 | 08/03/2023 14:32:22 |
| T-MRWD-1 | 850 | Planned Outage | 06/04/2023 | 20:00 | 17/08/2023 | 17/08/2023 | 10/08/2023 16:15:56 |
| T-MRWD-1 | 450 | Other | 17/08/2023 | 08:00 | 18/08/2023 | 18/08/2023 | 10/08/2023 16:12:54 |
| T-MRWD-1 | 450 | Planned Outage | 18/08/2023 | 20:00 | 19/08/2023 | 19/08/2023 | 10/08/2023 16:13:42 |