Below are the REMIT records that have been submitted by our staff.
| Unit | Capacity Reduction (MW) | Cause | Start Date | Start Time | Expected Return to Service From | Expected Return to Service To | Date Notified |
|---|---|---|---|---|---|---|---|
| T-MRWD-1 | 420 | Turbine | 28/11/2025 | 16:55 | 28/11/2025 | 28/11/2025 | 28/11/2025 17:32:29 |
| T-MRWD-1 | 450 | Other | 15/09/2025 | 19:45 | 15/09/2025 | 15/09/2025 | 15/09/2025 20:08:33 |
| T-MRWD-1 | 880 | Planned Outage | 13/04/2026 | 20:00 | 22/04/2026 | 22/04/2026 | 09/09/2025 14:17:25 |
| T-MRWD-1 | 440 | Turbine | 29/08/2025 | 05:30 | 29/08/2025 | 29/08/2025 | 29/08/2025 05:05:20 |
| T-MRWD-1 | 880 | Planned Outage | 23/10/2028 | 20:00 | 30/10/2028 | 30/10/2028 | 30/07/2025 14:23:33 |