Construction of the station took place between 2007 and 2009. A gallery containing photographs of the construction phase can be found below.
The CCGT was built under contract by Siemens plc and Siemens AG, companies who have a long track record in building these plants. Measures implemented to minimise the impact of construction works on the local community were bringing large equipment to site by water via the adjacent military port.
During construction of the underground gas pipeline (linking Marchwood Power to the country’s national gas transmission network) measures were implemented to minimise the impact of the work on the local community. Those working on the pipeline were required to follow best construction, safety management practices to comply with all planning conditions and local statutory requirements including health and safety.
At each stage during construction, Marchwood Power worked closely with the local authorities and the Environment Agency to ensure that the construction impact was carefully managed and in accordance with the planning conditions.
Gallery of images from the construction of the power station
- December 2007
- February 2008
- March 2008
- April 2008
- May 2008
- June 2008
- July 2008
- September 2008
- October 2008
- November 2008
- December 2008
- February 2009
- March 2009
- April 2009
- May 2009
- June 2009
- August 2009
- January 2010
- June 2011
- June 2012