Below are the REMIT records that have been submitted by our staff.
Unit | Capacity Reduction (MW) | Cause | Start Date | Start Time | Expected Return to Service From | Expected Return to Service To | Date Notified |
---|---|---|---|---|---|---|---|
T-MRWD-1 | 880 | Planned Outage | 04/01/2026 | 20:00 | 12/01/2026 | 12/01/2026 | 02/08/2023 09:50:15 |
T-MRWD-1 | 880 | Planned Outage | 19/11/2024 | 20:00 | 26/11/2024 | 26/11/2024 | 11/07/2019 14:57:46 |
T-MRWD-1 | 880 | Planned Outage | 10/10/2024 | 20:00 | 17/10/2024 | 17/10/2024 | 02/08/2023 09:49:30 |
T-MRWD-1 | 540 | Turbine | 17/04/2024 | 06:44 | 17/04/2024 | 17/04/2024 | 17/04/2024 05:59:12 |
T-MRWD-1 | 125 | Turbine | 28/03/2024 | 03:30 | 28/03/2024 | 28/03/2024 | 28/03/2024 04:02:09 |
Page 1 of 71 Next » |