Below are the REMIT records that have been submitted by our staff.
Unit | Capacity Reduction (MW) | Cause | Start Date | Start Time | Expected Return to Service From | Expected Return to Service To | Date Notified |
---|---|---|---|---|---|---|---|
T-MRWD-1 | 100 | Other | 25/06/2019 | 14:00 | 25/06/2019 | 25/06/2019 | 24/06/2019 13:04:50 |
T-MRWD-1 | 100 | Other | 21/08/2023 | 16:30 | 22/08/2023 | 22/08/2023 | 21/08/2023 15:50:54 |
T-MRWD-1 | 100 | Other | 24/08/2023 | 15:00 | 24/08/2023 | 24/08/2023 | 24/08/2023 12:36:31 |
T-MRWD-1 | 120 | Generator | 20/06/2018 | 05:08 | 20/06/2018 | 20/06/2018 | 20/09/2018 04:59:54 |
T-MRWD-1 | 125 | Turbine | 28/03/2024 | 03:30 | 28/03/2024 | 28/03/2024 | 28/03/2024 04:02:09 |
Page 1 of 71 Next » |